The URAL Automobile Plant is implementing a large-scale project to establish in-house production of drive axles and front axles for heavy-duty trucks and special purpose vehicles. The initiative covers 12 new production sections and marks a transition to a fundamentally new approach in manufacturing key transmission components. The project is being carried out with the support of the Industrial Development Fund (VEB.RF Group). Its strategic goal is not only to fully supply the URAL Automobile Plant with in-house produced axles, but also to expand into providing supplies to other Russian manufacturers of trucks and special purpose vehicles.
Construction work has been completed in the Powertrain Building: a reinforced foundation has been prepared over an area of 2,500 square meters, and the utility infrastructure has been almost completely upgraded. The modernization scale is driven by the increased power requirements of the new equipment.
As part of the power supply system upgrade, three transformer substations were installed, comprising a total of six transformers with a combined capacity of approximately 15 MW. In addition, busbars were laid, a modular compressor unit was installed, and pipeline routes for water and compressed air supply were constructed.
NAPI (National Industrial Information Agency)